Ethiopia starts partial power generation from Blue Nile dam - Los Angeles Times
Advertisement

Ethiopia starts partial power generation from Blue Nile dam

The dam has been a source of tension between Ethiopia and Sudan and Egypt.
(Mulugeta Ayene / Associated Press)
Share via

Ethiopia has started generating electricity from the controversial mega-dam that is being built on the Blue Nile.

The milestone was reached Sunday morning when one of the 13 turbines of the Grand Ethiopian Renaissance Dam started power generation in an event officiated by Prime Minister Abiy Ahmed.

“From now on, there will be nothing that will stop Ethiopia,†Abiy said.

Upon completion, it will be Africa’s largest hydroelectric dam.

A second officer injured in the crash of a Huntington Beach Police helicopter was released from the hospital Sunday morning.

“We just started generating power, but that doesn’t mean the project is completed,†said Kifle Horo, the dam’s project manager. “It will take from two and half to three years to complete it.â€

Advertisement

The dam, which will have a total power generating capacity of 6,500 megawatts, has been a source of tension between Ethiopia and the other riparian states, Sudan and Egypt. Ethiopia has already conducted two fillings of the dam, but the speed at which it will be filled and the amount of water that will be released during drought seasons remain unsolved.

Egypt fears a quick filling of the dam will reduce its share of Nile waters and seeks a legal agreement in case of a dispute.

Egypt’s Foreign Ministry said in a terse statement Sunday that Ethiopia’s move is another “breach†of the agreement of principles that the three countries signed in 2015. It didn’t elaborate.

Advertisement

Abiy, however, said the dam would benefit Egypt and Sudan as well.

“We want to export our pollution-free electricity to Europe through Sudan and Egypt, so the way forward is cooperation among us. Ethiopia doesn’t want and intend to harm anyone else,†he said.

Ethiopia contends the $4.2-billion dam is essential for its development and will enable it to distribute power to its population of more than 110 million.

Several rounds of talks have been held in attempts to solve the stalemate.

The dam’s construction started in 2011, and the completion date was missed years ago because of the embezzlement of funds and design flaws.

Advertisement