School district looks to renovate mistakes
Marisa OâNeil
Measure A, Newport-Mesa school districtâs massive, bond-funded,
multi-school renovation project, is entering its second year, and
many hope it will go smoother than the first.
When construction started on the first group of eight schools in
March of 2003 -- nearly simultaneously -- the district absorbed some
unpleasant surprises. Worse-than-anticipated termite and dry-rot
damage required extra attention. Plumbing issues meant some students
and teachers had to use portable toilets for months. Window
manufacturers dragged their feet, leaving students sitting in
classrooms with boarded-up windows on days hot enough to melt
crayons. And that was all at one school, Harbor View Elementary.
For some angry parents and staff members, it was too much too
soon.
âIf anything, we were overambitious,â said Paul Reed, assistant
superintendent of business services for Newport-Mesa Unified School
District.
This time, with the second group of seven schools, theyâre
staggering the start time of every project, keeping communication
lines open and trying their best to expect the unexpected.
And parents, staff and community members will be watching.
âWe have had our ups and downs with the process,â said Niki
Parker, chair of the Measure A oversight committee at Kaiser
Elementary School. âWe hope the district has been able to improve the
process, the scope and direction and provide more guidelines for the
next set of schools.â
Because the money for Measure A -- $110 million in local bonds and
another $63 million from the state -- is being divided between 28
schools, only the highest-priority work is being done. And some
things that need attention, such as athletic facilities and the Loats
Performing Arts Center at Newport Harbor High School, donât fall
under the improvement umbrella. Those must be paid for separately by
the district.
Since Proposition 13 restructured school funding in California,
Reed said most money goes into instruction and programs, not to
maintaining school buildings. Without preventive measures, the
schools fell into disrepair.
âIf we had been able to maintain our funding at the levels
recommended, it would have gone a long way to maintaining
facilities,â Reed said.
More confusion arose in the first group of schools about the role
each siteâs oversight committee should play in the process. Their
rights and duties werenât made clear, said Bob Rossen, chair for the
Woodland oversight committee, and members sometimes felt they were
ârubber stampingâ plans they didnât agree with.
Reed said the committees have input at the beginning of the
process, but once contractors are brought in, they canât run the
process.
âWe were the guinea pigs,â Rossen said. âThere were things that
went very well and things that didnât go well. I think as they get in
[groups of] two and three, they will improve on what theyâre going to
be doing.â
And at Harbor View Elementary, where just about everything that
could go wrong did, most of the major work has been done. But, some
parents say, little incomplete things are adding up, such as no poles
to open the new windows, no intercom system and dirt patches in need
of landscaping.
So far, things are going more smoothly at Group Two school Sonora
Elementary, parent Katrina Foley said.
âThereâs been no controversy,â Foley said. âI think we benefited a
lot from the schools that went before. When you have the opportunity
to correct a lot of problems that occurred in the first round and can
anticipate and avoid them, that helps.â
Work at Sonora should be complete by November.
Work at the other Group Two schools -- Davis Education Center and
College Park, Killybrooke and Wilson elementary schools -- will
progress through the summer and should be wrapped up later this year,
said Bonnie Martin, a director for project manager McCarthy Building
Companies. Things got off to an early start, she said, because some
schools agreed to vacate their administrative offices early and let
contractors get to work.
Wilson Elementary School, in its current state, serves as a
microcosm for all of Measure A and as an example of how the district
hopes the next phases will go.
The kindergarten classrooms, where tiny students sat only a couple
weeks ago, are stripped bare.
Across the campus, classrooms are nearing completion. New walls
housing four âdropsâ for Internet access, new windows, new tile,
multiple electrical outlets, refinished cupboards, new paint and new
carpet grace the rooms. All thatâs needed is some minor tweaking,
like a sink for washing little hands and a metal strip to marry the
carpet to the tile.
Where there were only two or three electrical outlets, there is
now one about every two feet. New wiring will support 16 computer
stations, Martin said.
The administration offices at Wilson are all but done. The smell
of fresh paint and carpet fills the bright rooms; a conference table
sits ready for teachers; boxes await unpacking; and new tile lines a
bathroomâs floors and walls.
âOne of the teachers stopped by last week and had not seen it
because it was fenced off before,â Principal Candy Sperling said.
âShe just about fell down when she saw it. She said: âThis looks like
a school.â It looked real shabby before. Now it looks like a school.
âI feel like the ugly duckling -- the one that swims around,
nobody loves him, then he turns into a swan.â
* MARISA OâNEIL covers education. She may be reached at (949)
574-4268 or by e-mail at [email protected].
All the latest on Orange County from Orange County.
Get our free TimesOC newsletter.
You may occasionally receive promotional content from the Daily Pilot.